Kenya’s Marine Spatial Plan (MSP) process is guided by global best practice and the provisions of the Physical and Land Use Planning Act no. 13 of 2019. The law mandates the State Department for Lands and Physical Planning to plan, develop and formulate safe and efficient use of the Kenya ocean space.

Kenya Marine Spatial Planning Process

(as per PLUPA, 2019)

Click on any step to learn more

Stakeholders Engagement
The MSP Process Design
1
Organization/Preparation pre-planning
Initial setup and groundwork for the MSP process, including assembling teams, securing resources, and establishing governance structures.
2
Defining and Analysing the Existing Situation
(Trend analysis encouraged)
Comprehensive assessment of current marine conditions, uses, conflicts, and trends to establish baseline understanding.
3
Predictive Scenario Building and Evaluation of Development Alternatives
Developing future scenarios and evaluating different development pathways to inform planning decisions.
4
Zoning and Policy Formulation
user and management regulations
Establishing spatial zones and developing policies for marine resource use and management.
5
Formulation of an Implementation Mechanism
Creating actionable frameworks and institutional arrangements for plan execution.
6
Preparation of the Monitoring and Evaluation Framework
Developing systems to track progress, measure outcomes, and assess plan effectiveness.
7
Validation
Formal review and confirmation of the plan's technical accuracy and stakeholder acceptance.
8
Publication of the Notice of Completion
(Form PLUPA 7) 14 days
Official announcement that the plan draft is complete and ready for public review.
9
Circulation of the Plan
(60 days)
Public consultation period allowing stakeholders to review and comment on the proposed plan.
10
Consideration of Comments
Systematic review and integration of feedback received during public consultation.
11
Publication of the Revised Plan
(Form PLUPA 7) 14 days
Release of the updated plan incorporating stakeholder feedback and revisions.
12
Approval of the Plan
Formal endorsement by relevant authorities granting legal status to the plan.
13
Issuance of Certificate of Approval
(Form PLUPA 8)
Official documentation certifying the plan's approval and authority for implementation.
14
Launch of the Plan
Official commencement of plan implementation and public announcement.
Monitoring and Evaluation
Adaptation
IMPLEMENTATION
OF THE PLAN

Source: The Kenya MSP process adopted from the IOC-UNESCO guide

Planning & Analysis
Policy & Framework
Validation
Public Consultation
Approval Process
Launch

Physical Contact

Office of The National Project Coorditnator, KEMFSED Maktaba Kuu Building, Ngong Road, Upper Hill, Mezzanine Floor, Nairobi